Wednesday, 28 November 2012
Property Lead Flashing
The common defects to flashing
When joining lead, over working may split they lead
Installing it wrong.
Materials
· 900mm lead. £120 (1)
· Lining paper 1m £5 (1)
· Cement £10 (1 bag)
· Sharp sand £10 (1 bag)
The defects and limitations of flashing
Its flexible when worked
It’s tough to bend to shapes
Lead corrodes
Tools
· Tin snips
· Lead dresser
· Pointing trowel
· Hammer and pug bolster
PPE
· Boots
· Gloves
· Goggles
· Dust mask
Plant hire
· Mobile tower £300 (1)
Risk assessment
· Getting lead poisoning
· cutting your hands.
We wear correct PPE. To prevent these risks from happening. To stop the lead getting into body wears mask and gloves to reduce the risk. wear gloves to prevent cuts when installing it and also keep hands away form tin snips when cutting the lead.
Method statement
We first got our PPE on, and then we made way to the area of work and started to tack the readings from they point to point so were they lead will fit in to the pug joints and sit. Then got a bit of lining paper to mark they points on and made it to fit then used to transfer it to they lead and fit in place. Then check if all is good and well finished (plus clearance).
Quote
Dear customer
We have inspected the lead flashing on roof and it has split so we need to replace it.
We first got lead and made way to house were we assembled a mobile tower to get to they area were the lead has split.
Started to rip out existing lead and then cut it to size and left a lip to put back in place and put back strong in place.
Sealed up any gapes then finished of work and pack away (plus clearness).
Times
8 hours
Cost
They coast of all they materials, mobile tower and labour will coast £ 965
• Materials £145
• Plant hire £300
• Ladour £40 per hour
• Overhead (petrol,PPE,permit) £200
Total cost £965